New rigid galvanised ductwork run between basement joists with every joint sealed

Air duct installation

What a duct installation day actually looks like

From survey to balancing: what happens on a duct installation, what is noisy, what needs the space clear, and what drives whether it is one day or several.

Installing ductwork is disruptive in a specific and predictable way, and knowing the sequence makes it much easier to plan around. Here is how a job runs.

Before the day: the survey

Nothing gets quoted from a floor plan. We measure the space the new run will serve, check what the existing system can carry, look at the route, and identify where support has to land and what has to be opened.

Two things get settled here that people often expect to settle later:

  • Whether the existing system has capacity. Adding a branch to a system that is already at its limit makes the new room mediocre and the existing rooms worse. If that is the situation, you should hear it before you spend anything.
  • Where the air will leave the new space. A supply with no return path produces a room that never reaches temperature. The return is planned at the same time as the supply, not afterwards.

Day one: protection and layout

Floors along the route get covered, corners get guarded, and the work area gets set up. Then the run is laid out physically: hangers and straps go in at proper intervals before any duct is hung, so nothing ends up resting on a joist edge or sagging between them.

This is the least visible part of the job and it determines how the system performs for the next twenty years.

Hanging and connecting

Rigid where rigid belongs, flex properly stretched where it does not. Connections are mechanically fastened rather than pushed together and hoped for.

This is the noisy phase. Cutting sheet metal, drilling into joists and fixing hangers are all loud, and if anyone in the house is working from home, this is the part to schedule around.

Sealing, before anything is closed in

Every joint gets mastic and mechanical fasteners while it can still be reached, and it gets photographed. A seam that will be behind insulation and drywall tomorrow has to be right today.

If your installer is not sealing before the insulation goes on, stop and ask when they intend to.

Making good

If ceilings or walls had to be opened, closing them up is its own scope. Ask at quoting time whether it is included, who does it, and to what standard: patched and ready to paint, or finished and painted. It is a common source of end-of-job disagreement and it is entirely avoidable by asking early.

Balancing and handover

The new registers are checked against the rest of the system, dampers are adjusted, and you get the photograph set of what is now behind the finishes.

The handover conversation should cover which room the new run serves, what to expect from it, and anything we found on the way that you should know about.

How long it takes

  • A single branch to one room, open access: usually a day.
  • A branch requiring finished ceilings to be opened: two days plus making good.
  • A full replacement across a house: several days, and it should be sequenced so the system is not down overnight in winter.

We give you the expected window when we quote, and we tell you which days are noisy and which need the space clear.

Working with other trades

We are frequently the duct crew on somebody else’s project. That works well as long as the sequencing is agreed: the ductwork has to be in, sealed and photographed before insulation and drywall, and the equipment side has to be settled before the branches are sized.

Tell us who is doing the equipment and when the drywall is scheduled, and we will fit around it.

What we need from you

  • Clear access to the work areas, including the attic hatch or crawlspace entry.
  • Somewhere to stage material.
  • Somewhere to park close enough to carry duct.
  • Pets kept away from open access points, which matters more than people expect with attic hatches and crawlspace doors.

The question worth asking at the end

Ask to see the photographs of the sealed joints before the insulation went on. If they exist, the work was done in the right order. If they do not, you have no way of knowing.

The installation service page covers the rest, and the design vocabulary that makes a quote easier to judge is here.

What people say

Five point zero, from 397 of them.

5.0

397 reviews on Google

  • Verified on Google
  • Licensed & insured
  • Veteran-owned

What reviewers mention most

  • 35a professional team
  • 11better airflow afterwards
  • 7before-and-after photos
  • 4a gas leak found on site
Read them on Google
  • Norma CruzMay 2026 · Google

    Leo and his team were professional and did a great job with the cleaning and the vent repair. Will definitely recommend

    Cleaning and vent repair

  • Melisande GittensApril 2026 · Google

    I had a great experience with your technicians Leo and Danny. The work professionally and communicate with the client. Thank you for your service!!

    Air duct cleaning

Free estimate

Tell us what the system is doing

We look before we quote, and the number we quote is the number you pay.

  • Quoted before any work starts
  • Floors covered before equipment comes in
  • Photographs of what we found and removed
  • No scare tactics, no surprise add-ons
(877) 824-9359

Open 24 hours, by appointment

So we know which crew is closest.

The system, the symptom and anything a technician should know before arriving.

No obligation. We reply the same day, and we book around the clock.

Rather talk to someone? Call (877) 824-9359 — open 24 hours, by appointment.